History
Our 80,000 gallon pool is the center gathering place of the community in the summer. It is also over 50 years old and each year the need for repairs and potential for problems increases.
The CBTB Pool Committee was formed and they did over a year's worth of research to come up with the best solution for the community and future CBTB generations. Here is their presentation: 05-28-2022 Pool Committee Presentation
On August 20, 2022 the Finance Committee made a presentation to explore options to pay for the pool. Following is the presentation and a link to a video recording of that meeting.
08-20-2022 Pool Funding Brief Video recording of 08-20-2022 Pool Funding Brief
On October 19, 2024 the current CBTB Pool Committee shared with the CBTB Board and attendees of the board meeting a presentation explaining the pool replacement specifications and asked the Board for approval to request bids. The request was approved and the bid information will be shared with interested contractors.
Pool Replacement Specification Approval Presentation
Pool and Site Design Proposal Requirements for CBTB (October 19, 2024)
At the December 2024 Board meeting the Finance Commitee presented finance information.
CBTB Pool Financing Feasibility Study (Dec '24)
Last update August 23, 2022
CBTB Pool Maintenance – Thursday, August 27
The CBTB pool will undergo some scheduled maintenance on Thursday, August 27, while our pool builder completes a repair to the plaster on the step in the sun shelf.
The pool will remain open and available for swimming during the maintenance. However, the sun shelf area may be temporarily unavailable while the work is being performed.
Beginning Wednesday, August 26, you may notice that the pool water level is lower than normal. This is intentional. We need to lower the water enough to expose the top of the step so the plaster repair can be completed and allowed to set properly.
Once the work is complete, the pool will be refilled to its normal operating level—the plaster likes being in the water too.
We appreciate everyone's patience while we complete this remaining item from the pool construction project. We're pleased to be checking another item off the final punch list!
CBTB Pool Committee
September 2025 New Pool Construction is About to Begin!
We’re excited to announce that demolition and construction of the new CBTB swimming pool will begin the week of October 6, 2025!
Please be aware that:
We appreciate everyone’s cooperation and understanding as this long-awaited project gets underway. It’s a big step forward for our community — thank you for helping us keep it safe and smooth.
If you have questions, feel free to contact a Board member at cbtbay@gmail.com or stop by the clubhouse bulletin board for updates.
– CBTB Board of Directors